Odoo 18 Manufacturing Explained - Advanced Configuration for Managing Production Plans

​​ ​In the second half of 2024, odoo18 quickly became a highly popular open-source solution upon its release. As the most comprehensive lightweight production management software, odoo integrates all the applications needed for smart manufacturing, including MRP, MES, PLM, quality control and inspection, shop floor management, and maintenance. A single open-source platform meets all your needs. Odoo18 helps manufacturing enterprises rapidly achieve digital transformation, reduce costs and increase efficiency, and move toward Industry 4.0.

Odoo 18 Manufacturing Analysis - Advanced Configuration for Production Planning

This article is the second part of managing manufacturing processes in Odoo: using the Manufacturing module's advanced configuration to manage multi-level BoMs, production kits, production planning, etc. ​

A production plan is a coordinated arrangement of production tasks by an enterprise, specifying the types, quantities, quality, and schedule of products to be produced. It is an important component of the enterprise's business plan and a key basis forproduction management. On one hand, the production plan is designed to meet the three key customer requirements: "delivery time, quality, and cost"; on the other hand, it enables the enterprise to obtain appropriate profits by planning the precise preparation, allocation, and use of the three production elements: "materials, personnel, andmachinery and equipment".


Odoo 18 Smart Manufacturing Series Articles
  1. Manufacturing Basic Settings (2025.01.09)
  2. Manufacturing Advanced Configuration (2025.01.24)
  3. Manufacturing Workflow
  4. Smart Factory Shop Floor Management
  5. Outsourcing and Subcontracting
  6. Reports
  7. Barcode Setup and Application
  8. Quality Check Setup and Application
  9. PLM Product Lifecycle
  10. Production Equipment Maintenance

1. Advanced Configuration

1.1. Manage Product Variant BoMs

Odoo allows multiple variants of the same product to use a single Bill of Materials (BoM). Consolidating BoMs for products with variants avoids managing multiple BoMs, saving time.

 

1.1.1. Activate Product Variants

To activate the product variants feature, navigate to Inventory app ‣ Configuration ‣ Settings and scroll down to the Products section. Then, check the box to enable the Variants option. Then, click Save to apply the settings.

1.1. Manage Product Variant BoMs

 

1.1.2. Create Custom Product Attributes

After activating the product variants feature, create and edit product attributes on the Variants page.

Click the Attributes button to access the Attributes page from Inventory app ‣ Configuration ‣ Settings, or click Inventory app ‣ Configuration ‣ Attributes to access the Attributes page.

Once on the Attributes page, click an existing attribute or click Create to create a new one. Clicking Create displays a new blank form for custom attributes. For existing attributes, click Edit on their form to make changes.

Select Attribute Name and pick a category from the dropdown of the Category field. Then choose the desired option next to the Display Type and Variant Creation Mode fields. Once done, click Add a line under the `Attribute Values` tab to add a new value.

For example, multi-color garments:

Create a new attribute [Color]; after specifying the color here, you can configure different prices for different attributes.

1.1. Manage Product Variant BoMs

 

1.1.3. Add Product Variants on the Product Form

The created attributes can be applied to specific variants of a specific product. To add product variants to a product, navigate to the product form by going to Inventory app --> Products --> Products. To make changes to the product, click Edit. Then, click `the Variants tab.

Under the Attributes heading, click Add a line to add a new attribute, then select the attribute to add from the dropdown menu.

Then, under the Values heading, click the dropdown menu to select from the list of existing values. Click each desired value to add them, and repeat this process for any other attributes added to the product.

When done, click Save to save the changes.

For example, multi-color garments:

You can add different color values and different size values.

1.1. Manage Product Variant BoMs

 

1.1.4. Apply BOM Components to Product Variants

Then, create a new Bill of Materials (BoM). Or go to Manufacturing app ‣ Products ‣ Bills of Materials to edit an existing BoM. Then, click Create to open a new Bill of Materials form and configure it from scratch.

Each component can be assigned to multiple variants. Components without a specified variant will be used in every variant of the product. The same principle applies to configuration operations and by-products.

For example, multi-color garments:

Assuming the T-shirts all have the same base color but require different colored buttons, you need to specify different colored accessories for each color variant in the BOM table.

1.1. Manage Product Variant BoMs

 

1.1.5. Sell and Manufacture Variants of BoM Products

To sell and manufacture variants of a BoM (Bill of Materials) product, navigate to the Sales app –> Create to create a new quotation.

 

1.1.6. Sell Variants of BoM Products

After entering the blank Quotation form, click the drop-down menu next to the Customer field to add a customer.

Then, under the Order Lines tab, click Add a product and select the previously created BoM (bill of materials) product with variants from the drop-down menu. This opens a Configure Product window.

1.1. Manage Product Variant BoMs

 

When ready, click Confirm to close the pop-up window.

Then, click Save to save all changes, and click Confirm at the top of the Quotation form to create and confirm the new sales order (SO).

 

1.2. Using Kits

In Odoo,*A kit* is a type of Bill of Materials (BoM) that can be manufactured and sold. Kits are a set of unassembled components sold to customers. They can be sold as standalone products, but are also a useful tool for managing more complex Bills of Materials (BoMs).

To use, manufacture, and sell kits, both the Manufacturing and Inventory apps need to be installed.

 

1.2.1. Create a Kit as a Product

To use a kit as a sellable product, or simply as a component organization tool, you should first create the kit as a product.

To create a kit product, go to Inventory app ‣ Products ‣ Products, then click Create.

Then, assign a name to the new kit product. Next, under the General Information tab, set the Product Type to Consumable. Kit products work best as consumables because kit inventory is typically not tracked.

Note

While kits should almost always be set as Consumable , companies using the **Anglo-Saxon** accounting regime may need to create kits as Storable Product. This is because the cost of goods sold (COGS) is recorded in the accounting journal when invoicing kits.

Unlike storable products, the Inventory tab path specification does not matter for kits, as Odoo replenishes kits using the routes of their components. All other parameters of the kit product can be modified as preferred. Once ready, click Save to save the new product.

Kit components must also be configured as products via Inventory app ‣ Products ‣ Products. These components require no special configuration.


1.2.2. Set Kit BoM

After fully configuring the kit product and its components, a new BoM (Bill of Materials) can be created for the kit product.

To do so, go to the Manufacturing app ‣ Products ‣ Bills of Materials, and click Create. Next to the Product field, click the drop-down menu to reveal the list of products, and select the previously configured kit product.

Then, in the BoM Type field, select the Kit option. Finally, under the Components tab, click Add a line to add each required component, and specify its quantity in the Quantity column.

When ready, click Save to save the newly created BoM (Bill of Materials).

1.2. Using Kits

If the kit is used only as a sellable product, you only need to add components under the Components tab; no production operations need to be configured.

Note

When a kit is sold as a product, it appears as a single line item on quotations and sales orders. However, on delivery orders, each component of the kit is listed.


1.2.3. Using Kits to Manage Complex BoMs

Kits are also used to manage multi-level BoMs (bills of materials). These products contain **other** BoM (bill of materials) products as components, so nested BoMs (bills of materials) are required. Incorporating pre-configured kits into multi-level BoMs (bills of materials) allows bundled products to be organized more concisely.

To configure this type of BoM (bill of materials) with kits as components, go to Manufacturing app ‣ Products ‣ Bills of Materials, then click Create.

Next to the Product field, click the drop-down menu to display the product list, then select the desired BoM (Bill of Materials) product. Then, in the BoM Type field, select the Manufacture this product option.

Under the Components tab, click Add a line and select the kit as a component. Once the kit is added as a component, there is no need to add the kit's components separately. Any BoM Type can be used for the BoM (bill of materials) of the parent product.

When ready, click Save to save your changes.

 

1.2.4. Structure & Cost

To fully understand the components of a multi-level Bill of Materials (BoM), click the Structure & Cost smart button. Child BoMs can be expanded and viewed from this report.

If a multi-level BOM is included in the BOM table, the system will automatically calculate the cost of components contained in all levels of the BOM.

1.2. Using Kits

When creating a manufacturing order for a product with a multi-level bill of materials (BoM), kit products are automatically expanded to show all components. Any operations in the kit's BoM (bill of materials) are also added to the manufacturing order's work order list.

 

 

1.3. Manage Production Planning

There are multiple ways to manage manufacturing order automation for products with multi-level BoMs (bills of materials).

Semi-finished products are specifically used to manage manufacturable products with multi-level BoMs. If a BoM is created only to organize components or bundle sellable products, use Kit is a more appropriate choice.

There are two options to automatically trigger semi-finished product manufacturing orders after confirming the main product manufacturing order:

Option 1 (Recommended): Create a reordering rule for the semi-finished product and set the minimum and maximum required stock quantities to `0`.

Option 2: Activate Make to Order (MTO) and Manufacturing routes under the Inventory tab of the semi-finished product form.

 

Option 1 is more flexible than Option 2 and is therefore recommended. Reordering rules do not directly link demand to replenishment, thus allowing reserved stock to be unreserved and redirected to other orders if necessary. The Make to Order (MTO) route creates a dedicated link between semi-finished and top-level products, specifically reserving quantities for confirmed top-level manufacturing orders.

Regardless of the method chosen, the semi-finished product must be fully manufactured before starting production of the top-level product.

 

 

1.4. Manage Work Orders Using Work Centers

The Odoo Manufacturing app allows work orders to be executed at specific work centers. When creating a manufacturing order for a product, any work orders listed in the Operations tab of the product's bill of materials (BoM) will also be automatically created and assigned to the designated work center. Work orders can be managed in the Manufacturing module by selecting Operations ‣ Work Orders.

To use work centers, the work orders feature must first be enabled. To do this, go to the Manufacturing module, select Configuration --> Settings, and then activate the checkbox next to Work Orders. Work centers can then be created and managed by selecting Configuration --> Work Centers`.

1.4. Manage Work Orders Using Work Centers

 

1.4.1. Create a Work Center

In the Manufacturing` module, select `Configuration --> Work Centers --> Create. Then fill out the work center form as shown below:

Work Center Name: Provide a concise name for the work center that describes the type of operation it will be used for

1.4. Manage Work Orders Using Work Centers

 

Alternative Work Centers: Specify alternative work centers where operations should be performed when the primary work center is unavailable

1.4. Manage Work Orders Using Work Centers


Working Hours: Define the number of hours the work center is available each week. Leave blank for no limit.

1.4. Manage Work Orders Using Work Centers

 

1.4.2. Set Work Center Productivity Standards

The General Information tab on the work center form allows you to specify productivity targets for the work center:

l Time Efficiency: Used to calculate the expected duration of a work order at the work center; for example, if a work order normally takes one hour and the efficiency is set to 200%, the work order will take 30 minutes.

l Capacity: The default number of units (in product UoM) that can be produced in parallel (simultaneously) at this work center. For example, if capacity is 5 and you need to produce 10 units, the operation time listed on the BOM will be multiplied by 2. But note! The time before and after production is only calculated once.

l OEE Target: The efficiency target for the work center.

l Setup Time: The setup time required before starting work.

l Cleanup Time: The time required for breakdown or cleanup after work is completed.

l Cost per Hour: The cost of running the work center for one hour.

l Analytic Account: The account for recording work center costs.

1.4. Manage Work Orders Using Work Centers

 

1.4.3. Integrate IoT Devices

The IoT Triggers tab can`integrate IoT (Internet of Things) devices with the work center:

Device: Specify the IoT device to trigger.

Key: The security key of the device.

Action: The IoT device action to trigger.

1.4. Manage Work Orders Using Work Centers

 

1.4.4. Use Case: Configure an Alternative Work Center

When a work center is at full capacity, it cannot accept any new work orders. Instead of waiting for the work center to become available, designate an alternative work center to perform the excess work orders.

First, create a new work center. Configure the Equipment tab so that it has all the same equipment as the main work center. This will ensure that both work centers can perform the same tasks. Navigate to the main work center and include the new work center in the Alternative Work Centers selection field.

Now, create a new manufacturing order and use the main work center in one of its operations. The main work center will be automatically selected in the Work Orders tab. After confirming the manufacturing order, click the Plan button in the upper left corner of the table.

1.4. Manage Work Orders Using Work Centers

If the capacity of the main work center is full, the work center selected for the operation will automatically change to an alternative work center.

1.4. Manage Work Orders Using Work Centers

 

1.4.5. Monitor Work Center Performance

The performance of an individual work center can be viewed by selecting Configuration ‣ Work Centers and clicking on a work center. Various metrics showing the performance of the work center can be viewed in the upper right corner of the table:

OEE: Overall Effective Efficiency, i.e., the percentage of time the work center is fully productive

Loss: The amount of time lost due to downtime

Load: The time required to complete the current work

Performance: Actual working time, expressed as a percentage of the expected time

 

 

1.5. Work Order Dependencies

When manufacturing certain products, it may be necessary to complete specific operations before others can begin. To ensure that operations are performed in the correct order, Odoo Manufacturing has a *Work Order Dependencies* setting. When this setting is enabled, operations on the Bill of Materials (BoM) will be *blocked* by other operations that should be performed first.

 

1.5.1. Configuration

*The *Work Order Dependencies* setting is not enabled by default. To enable it, first navigate to Manufacturing ‣ Configuration ‣ Settings. Then, enable the Work Orders setting (if not already active).

After enabling the Work Orders setting, the Work Order Dependencies setting will appear below. Enable Work Order Dependencies, then click `Save` to confirm the changes.

1.5. Work Order Dependencies


1.5.2. Add Dependencies to a BoM

Work order dependencies are configured on the product's |BOM|. To do this, navigate to Manufacturing ‣ Products ‣ Bills of Materials, then select a BoM, or click New to create a new BoM.

In the BoM, click the Miscellaneous tab, then enable the Operation Dependencies checkbox.1.5. Work Order Dependencies

This will add a new flexible consumption option group to the settings in the Operations tab.

 

 

Used to define whether you can consume more or fewer components than the quantity defined on the BoM:

* Allowed: Allowed for all manufacturing users.

* Allowed with warning: Allowed for all manufacturing users, with a consumption difference summary displayed upon closing. Note that in cases where components are highlighted for consumption, consumption warnings will still be issued when appropriate, even if consumption is only recorded manually.

*Blocking: When BoM consumption is not followed, only managers can close manufacturing orders.

 

On the line of an operation that should be blocked by others, click the Blocked field, and the Open: Operation` popup appears. In the  `Blocked drop-down field of the popup, select the blocking operation that must be completed *before* the blocked operation.

For example: the cutting work needs to be completed before painting.

1.5. Work Order Dependencies

Finally, click Save to save the BoM.

 

1.5.3. Planning Work Orders Using Dependencies

Once work order dependencies are configured on a BoM, Odoo Manufacturing can schedule when to plan work orders based on the work order dependencies. To plan work orders for a manufacturing order, first navigate to Manufacturing ‣ Operations ‣ Manufacturing Orders.

Next, select a manufacturing order for the product and set work order dependencies on its BoM, or create a new manufacturing order by clicking New. If creating a new manufacturing order, select the BoM from the Bill of Materials dropdown field to configure work order dependencies, then click Confirm.

After confirming the manufacturing order, select the Work Orders tab to view the work orders required to complete the production order. In the Status section, any work order not blocked by other work orders will display the Ready label.

Work orders blocked by one or more work orders will display the Waiting for Another Work Order label. Once the blocking work order is completed, the label will update to Ready.

1.5. Work Order Dependencies

To plan the work orders of a manufacturing order, click the Plan button at the top of the page. This will automatically fill in the Scheduled Start Date field for each work order on the Work Orders tab with the planned start date and time. Blocked work orders will be scheduled at the end of the time period specified in the Expected Duration field of the preceding work order.

1.5. Work Order Dependencies1.5. Work Order Dependencies

 

1.5.4. Shop Floor

To view a visual representation of the work order plan, navigate to the Work Order Plan page via Manufacturing ‣ Planning ‣ Plan by Work Center. This page displays a timeline of all work orders planned for each operation.

If a work order is blocked by the completion of another work order, the blocked work order will be shown as scheduled to start after the blocking work order. Additionally, there will be an arrow between the two work orders, pointing from the blocking work order to the blocked work order.

1.5. Work Order Dependencies


Non-standard Scheduling: Put "Uncertainty" into the Plan First

For non-standard orders, the BOM and work hours are often only estimates before production starts. A plan scheduled according to standard processes may be disrupted by changes the next day. A more realistic approach is segmented scheduling: lock long-lead materials by project first, run design and procurement in parallel; schedule work orders by work center and bottleneck operations, and reserve buffers for changes; when changes occur, only reschedule the affected segment.

The productivity standards of work centers and alternative work centers should also be properly configured, so that temporary equipment changes do not cause line stoppages. For non-standard manufacturing ERP scheduling, accept uncertainty first, then talk about optimization.

 Odoo Smart: Odoo 100% Success
Professional Odoo Development & Implementation, formerly Guangzhou Shangpeng
  • 100% successful Odoo project delivery in China and overseas
  • Ranked first for Odoo official website downloads, serving thousands of enterprises
  • The #1 Best-Selling Chinese Company on the Odoo Website
  • Certified Service Provider for DingTalk and WeCom
  • Microsoft China ChatGPT Service Provider, AI Center
  • Baidu Qianfan and Alibaba Tongyi Qianwen Service Provider
  • 11 Years of Odoo Expertise, Controllable Full-Source Delivery
  • Odoo Chinese App Store, massive modules 
Odoo 18 Manufacturing Explained - Advanced Configuration for Managing Production Plans